Running account bills
Seven bills, ₹5.2 Cr claimed, and a certification cycle that has gone from 41 days to 14. Bills built from certified measurements do not come back with queries.
RA bill register
| Bill | Period | Gross | Certified | Net paid | Days | Status |
|---|---|---|---|---|---|---|
Feb–Mar 2025 Certified with 5.6% deduction for unmeasured excavation. | ₹42,18,400 | ₹39,84,100 | ₹33,86,485 | 41 | Paid | |
Apr–May 2025 Foundation and raft complete. | ₹61,92,300 | ₹58,11,000 | ₹49,39,350 | 36 | Paid | |
Jun–Jul 2025 ₹7.42 L held pending cube test certificates for L02–L04. | ₹78,44,900 | ₹71,02,200 | ₹60,36,870 | 33 | Paid | |
Aug–Oct 2025 First bill drafted by the RA agent from certified MB entries. | ₹94,10,600 | ₹91,88,000 | ₹78,09,800 | 26 | Paid | |
Nov 2025–Jan 2026 Escalation under Clause 10CA applied for steel — ₹3.11 L. | ₹1,12,66,000 | ₹1,10,04,400 | ₹93,53,740 | 19 | Paid | |
Feb–May 2026 Certified in 14 days. Payment due under the 45-day MSME clock. | ₹1,28,40,200 | ₹1,25,92,600 | ₹1,07,03,710 | 14 | Certified | |
Jun–Aug 2026 Drafted by the RA agent. Awaiting PMC certification. | ₹9,76,654 | — | ₹6,79,969 | — | Draft | |
| Total claimed / certified | ₹5.27 Cr | ₹4.97 Cr | ||||
Days from measurement to certification
First three bills averaged 37 days. The last three averaged 20. On a ₹68 Cr contract at 14%, that difference is roughly ₹9.6 L of financing the contractor no longer carries.
RA-01 to RA-06 · submission to certification datesBank guarantees, EMD and retention — cash nobody watches
Performance BG
BG-2211
Canara Bank, Whitefield
₹3.40 Cr
101 days to expiry
5% of contract value. Valid.
Mobilisation advance BG
BG-2244
HDFC Bank, Marathahalli
₹7.48 Cr
24 days to expiry
Bond is 110% of the ₹6.80 Cr advance. Expires in 24 days with ₹1.92 Cr still unrecovered — extend or recover.
EMD
EMD-0912
Canara Bank
₹12 L
12 days to expiry
Bid concluded 14 months ago. EMD not released — ₹12 L of dead capital.
Retention
RET-SNH
Meridian Estates (withheld)
₹2.47 Cr
DLP + 12 months
5% withheld across RA-01 to RA-06. No release schedule agreed in writing.