Portfolio assurance
Progress you can show your lender, backed by evidence.
Sunrise Heights
At Risk6 percentage points of claimed progress carry no evidence. Four floors are entirely unobserved.
Meridian Downtown
SupportedClaimed and certified agree within 0.7%. This is what a defensible QPR looks like.
Green Verge Phase II
Contradicted₹3.58 Cr withdrawn against progress that cannot be evidenced, and the escrow is ₹3.34 Cr short of the 70% requirement. This is the file that costs a promoter their registration.
A RERA quarterly progress report built on certified measurement, not on a contractor’s letter. Four floors on Sunrise Heights carry no evidence, so the QPR does not claim them.
Withdrawals require joint architect, engineer and CA certification against percentage completion. Green Verge drew ₹3.58 Cr ahead of what could be certified. That is the file that costs a promoter their registration.
Every bank applies a haircut to self-reported progress. Evidence-backed progress is the only kind that does not get one.