Plan & buy

Subcontractors & back-to-back billing

Six work orders, ₹9.7 Cr of committed value, and every subcontractor claim reconciled against what the main contract actually certified for the same work.
Work order value
₹9.72 Cr
6 active work orders
Certified upstream
₹4.72 Cr
what the client has certified for this work
Claimed by subs
₹5.01 Cr
what the subcontractors have applied for
Unreconciled gap
₹28.40 L
paid out of your own margin unless resolved

Sri Lakshmi Constructions

ContradictedMSME · 45-day clock
WO-101 · RCC & blockwork labour · 187 workers on the muster
Claim vs certification
+₹26.80 L
Work order
₹4,84,00,000
Certified upstream
₹3,11,40,000
Claimed by sub
₹3,38,20,000
Paid
₹3,02,60,000

Sub claims ₹26.80 L more than the main contract certified for the same work. Two floors of the difference sit on A-16 and A-17, which carry no evidence at all.

retention held ₹15,57,000 · released against defect-liability milestones

Vishwa Waterproofing

At RiskMSME · 45-day clock
WO-104 · Waterproofing systems · 22 workers on the muster
Claim vs certification
Work order
₹62,00,000
Certified upstream
₹41,20,000
Claimed by sub
₹41,20,000
Paid
₹36,10,000

Claims reconcile exactly. But 240 sqm of membrane was received with no gate evidence — consumption is unwitnessed.

retention held ₹2,06,000 · released against defect-liability milestones

Ravindra Electricals

SupportedMSME · 45-day clock
WO-108 · Internal electrification · 41 workers on the muster
Claim vs certification
Work order
₹1,18,00,000
Certified upstream
₹48,60,000
Claimed by sub
₹47,90,000
Paid
₹44,10,000

Every claim maps to a certified main-contract line. Nothing outstanding.

retention held ₹2,43,000 · released against defect-liability milestones

Nandi Plastering Works

At RiskMSME · 45-day clock
WO-111 · Internal & external plaster · 76 workers on the muster
Claim vs certification
+₹2.30 L
Work order
₹88,00,000
Certified upstream
₹52,80,000
Claimed by sub
₹55,10,000
Paid
₹49,20,000

₹2.30 L claimed against plaster on A-07, where cement consumption is 11.4% over theoretical. Hold until reconciled.

Working onA-05A-06A-07
retention held ₹2,64,000 · released against defect-liability milestones

Deccan Tiling Co.

SupportedMSME · 45-day clock
WO-114 · Flooring & dado · 34 workers on the muster
Claim vs certification
Work order
₹74,00,000
Certified upstream
₹18,40,000
Claimed by sub
₹18,40,000
Paid
₹14,90,000

Early stage. Claims match certification.

Working onA-01A-02
retention held ₹92,000 · released against defect-liability milestones

Skyline Aluminium

Unobserved
WO-117 · Doors, windows & glazing · 0 workers on the muster
Claim vs certification
Work order
₹1,46,00,000
Certified upstream
₹0
Claimed by sub
₹0
Paid
₹0

Work order issued 11 Aug. No mobilisation, no measurement, nothing to verify yet.

retention held ₹0 · released against defect-liability milestones
Labour on site today · 21 Aug 2026
muster roll · BOCW and PF/ESI registers derive from this
412
on the muster roll
Biometric verified366
GPS verified at a work face341
On the muster, unverified46

46 workers are on the muster with no biometric punch. That is not an accusation of a ghost worker — it is an Unobserved attendance, and it is what the wage register will be audited on.

By trade
Mason
84₹920/day
Bar bender
46₹980/day
Carpenter (shuttering)
61₹950/day
Helper — male
132₹720/day
Helper — female
58₹690/day
Plumber
18₹880/day
Electrician
13₹900/day