Weighted score 80.5. Evidence coverage 88%. Two rules sit above this arithmetic: over 8% material variance or an open critical NCR forces Contradicted; under 30% evidence forces Unobserved regardless of how good the numbers look.
BOQ items on this floor
Item
Planned
Measured
Certified
Verdict
BOQ 4.2
RCC M25 in slabs, beams & landings incl. shuttering and finishing
76
60
56
Supported
BOQ 5.1
Brickwork 230mm thick in CM 1:6 with second class red bricks
66
53
49
Supported
BOQ 6.4
12mm cement plaster in CM 1:4 to internal walls
336
285
266
Supported
BOQ 8.3
Vitrified tile flooring 600×600 laid on 20mm CM 1:4 bed
284
236
220
Supported
BOQ 9.1
APP membrane waterproofing to toilets and terrace incl. screed
358
299
279
Supported
Material reconciliation — theoretical vs actual
Material
Theoretical
Actual
Variance
At risk
OPC 53 cement
store issue register · 5 slips
98.11 bag
103.8 bag
+5.8%
₹2,327
TMT Fe550
store issue register · 3 slips
3.39 T
3.53 T
+4.0%
₹8,176
M-sand
store issue register · 10 slips
31.34 T
32.62 T
+4.1%
₹1,459
20mm aggregate
store issue register · 10 slips
37.88 T
39.28 T
+3.7%
₹1,372
Red brick
store issue register · 6 slips
4,075.89 no
4,230.77 no
+3.8%
₹1,378
Anything above 8% is Contradicted. Cement does not evaporate — it walks out of the gate.