Weighted score 96.6. Evidence coverage 97%. Two rules sit above this arithmetic: over 8% material variance or an open critical NCR forces Contradicted; under 30% evidence forces Unobserved regardless of how good the numbers look.
BOQ items on this floor
Item
Planned
Measured
Certified
Verdict
BOQ 4.2
RCC M25 in slabs, beams & landings incl. shuttering and finishing
51
48
46
Supported
BOQ 5.1
Brickwork 230mm thick in CM 1:6 with second class red bricks
64
60
58
Supported
BOQ 6.4
12mm cement plaster in CM 1:4 to internal walls
285
284
273
Supported
BOQ 8.3
Vitrified tile flooring 600×600 laid on 20mm CM 1:4 bed
280
268
257
Supported
BOQ 9.1
APP membrane waterproofing to toilets and terrace incl. screed
340
328
315
Supported
Material reconciliation — theoretical vs actual
Material
Theoretical
Actual
Variance
At risk
OPC 53 cement
store issue register · 4 slips
105.66 bag
110.63 bag
+4.7%
₹2,033
TMT Fe550
store issue register · 7 slips
4.27 T
4.4 T
+3.0%
₹7,592
M-sand
store issue register · 8 slips
37.94 T
38.62 T
+1.8%
₹775
20mm aggregate
store issue register · 7 slips
41.31 T
43.09 T
+4.3%
₹1,744
Red brick
store issue register · 8 slips
4,926.3 no
5,128.28 no
+4.1%
₹1,798
Anything above 8% is Contradicted. Cement does not evaporate — it walks out of the gate.