A critical non-conformance is open against structural work on this floor.
How this verdict was computed
BOQ quantity complete54×0.40
MB pages 180–219 · 5 items
Checklist pass rate51×0.20
stage QA checklist register
RA-bill certified22×0.20
RA-06 certified abstract
NCR burden (inverted)81×0.10
6 NCRs on this floor
Schedule slip (inverted)78×0.10
programme baseline rev 4
Weighted score 52.1. Evidence coverage 58%. Two rules sit above this arithmetic: over 8% material variance or an open critical NCR forces Contradicted; under 30% evidence forces Unobserved regardless of how good the numbers look.
BOQ items on this floor
Item
Planned
Measured
Certified
Verdict
BOQ 4.2
RCC M25 in slabs, beams & landings incl. shuttering and finishing
74
39
16
At Risk
BOQ 5.1
Brickwork 230mm thick in CM 1:6 with second class red bricks
69
37
15
At Risk
BOQ 6.4
12mm cement plaster in CM 1:4 to internal walls
328
178
71
At Risk
BOQ 8.3
Vitrified tile flooring 600×600 laid on 20mm CM 1:4 bed
315
172
69
At Risk
BOQ 9.1
APP membrane waterproofing to toilets and terrace incl. screed
360
199
79
At Risk
Material reconciliation — theoretical vs actual
Material
Theoretical
Actual
Variance
At risk
OPC 53 cement
store issue register · 11 slips
63.68 bag
66.48 bag
+4.4%
₹1,145
TMT Fe550
store issue register · 9 slips
2.33 T
2.36 T
+1.5%
₹1,752
M-sand
store issue register · 11 slips
19.73 T
20.44 T
+3.6%
₹809
20mm aggregate
store issue register · 3 slips
24.62 T
25.46 T
+3.4%
₹823
Red brick
store issue register · 2 slips
2,548.97 no
2,666.22 no
+4.6%
₹1,044
Anything above 8% is Contradicted. Cement does not evaporate — it walks out of the gate.