A critical non-conformance is open against structural work on this floor.
How this verdict was computed
BOQ quantity complete71×0.40
MB pages 180–219 · 5 items
Checklist pass rate62×0.20
stage QA checklist register
RA-bill certified44×0.20
RA-06 certified abstract
NCR burden (inverted)77×0.10
4 NCRs on this floor
Schedule slip (inverted)80×0.10
programme baseline rev 4
Weighted score 65.3. Evidence coverage 69%. Two rules sit above this arithmetic: over 8% material variance or an open critical NCR forces Contradicted; under 30% evidence forces Unobserved regardless of how good the numbers look.
BOQ items on this floor
Item
Planned
Measured
Certified
Verdict
BOQ 4.2
RCC M25 in slabs, beams & landings incl. shuttering and finishing
60
43
26
At Risk
BOQ 5.1
Brickwork 230mm thick in CM 1:6 with second class red bricks
73
52
32
At Risk
BOQ 6.4
12mm cement plaster in CM 1:4 to internal walls
266
197
120
At Risk
BOQ 8.3
Vitrified tile flooring 600×600 laid on 20mm CM 1:4 bed
294
205
125
At Risk
BOQ 9.1
APP membrane waterproofing to toilets and terrace incl. screed
353
256
155
At Risk
Material reconciliation — theoretical vs actual
Material
Theoretical
Actual
Variance
At risk
OPC 53 cement
store issue register · 3 slips
88.92 bag
87.94 bag
-1.1%
—
TMT Fe550
store issue register · 4 slips
2.84 T
2.86 T
+0.7%
₹1,168
M-sand
store issue register · 2 slips
27.46 T
27.6 T
+0.5%
₹160
20mm aggregate
store issue register · 8 slips
34.23 T
34.26 T
+0.1%
₹29
Red brick
store issue register · 5 slips
3,204.07 no
3,184.85 no
-0.6%
—
Anything above 8% is Contradicted. Cement does not evaporate — it walks out of the gate.