Tower A · Level 16

RCC frame — reported complete

Verdict override applied

Only 21% of claims on this floor carry evidence. Reported progress of 88% is unverified — this is not a low score, it is an absent one.

How this verdict was computed
BOQ quantity complete88×0.40
MB pages 180–219 · 5 items
Checklist pass rate0×0.20
no checklist filed
RA-bill certified0×0.20
nothing certified yet
NCR burden (inverted)89×0.10
0 NCRs on this floor
Schedule slip (inverted)78×0.10
programme baseline rev 4

Weighted score 51.9. Evidence coverage 21%. Two rules sit above this arithmetic: over 8% material variance or an open critical NCR forces Contradicted; under 30% evidence forces Unobserved regardless of how good the numbers look.

BOQ items on this floor
ItemPlannedMeasuredCertifiedVerdict
BOQ 4.2
RCC M25 in slabs, beams & landings incl. shuttering and finishing
51470Unobserved
BOQ 5.1
Brickwork 230mm thick in CM 1:6 with second class red bricks
77680Unobserved
BOQ 6.4
12mm cement plaster in CM 1:4 to internal walls
3863330Unobserved
BOQ 8.3
Vitrified tile flooring 600×600 laid on 20mm CM 1:4 bed
2992680Unobserved
BOQ 9.1
APP membrane waterproofing to toilets and terrace incl. screed
2742450Unobserved
Material reconciliation — theoretical vs actual
MaterialTheoreticalActualVarianceAt risk
OPC 53 cement
no issue slips filed
113.58 bag116.76 bag+2.8%₹1,301
TMT Fe550
no issue slips filed
3.87 T3.94 T+1.8%₹4,088
M-sand
no issue slips filed
29.61 T30.65 T+3.5%₹1,186
20mm aggregate
no issue slips filed
35.07 T35.11 T+0.1%₹39
Red brick
no issue slips filed
4,086.6 no4,135.64 no+1.2%₹436

Anything above 8% is Contradicted. Cement does not evaporate — it walks out of the gate.

Open non-conformances
No inspection on record

Zero NCRs here does not mean zero defects. Nobody has walked this floor with a checklist, so there is nothing to report either way. That is why this floor is grey.

Linked documents

One drawing and nothing else. No measurement book page, no goods receipt, no test certificate, no photograph. The site engineer reports 88% complete and there is no way to check.

Site photographs
No photographs captured on this floor in the last 30 days.