Weighted score 93.5. Evidence coverage 97%. Two rules sit above this arithmetic: over 8% material variance or an open critical NCR forces Contradicted; under 30% evidence forces Unobserved regardless of how good the numbers look.
BOQ items on this floor
Item
Planned
Measured
Certified
Verdict
BOQ 4.2
RCC M25 in slabs, beams & landings incl. shuttering and finishing
59
60
56
Supported
BOQ 5.1
Brickwork 230mm thick in CM 1:6 with second class red bricks
62
59
55
Supported
BOQ 6.4
12mm cement plaster in CM 1:4 to internal walls
398
398
370
Supported
BOQ 8.3
Vitrified tile flooring 600×600 laid on 20mm CM 1:4 bed
305
318
296
Contradicted
BOQ 9.1
APP membrane waterproofing to toilets and terrace incl. screed
365
374
348
Contradicted
Material reconciliation — theoretical vs actual
Material
Theoretical
Actual
Variance
At risk
OPC 53 cement
store issue register · 9 slips
124.97 bag
129.84 bag
+3.9%
₹1,992
TMT Fe550
store issue register · 11 slips
3.7 T
3.84 T
+3.9%
₹8,176
M-sand
store issue register · 5 slips
32.45 T
32.68 T
+0.7%
₹262
20mm aggregate
store issue register · 10 slips
39.49 T
40.2 T
+1.8%
₹696
Red brick
store issue register · 3 slips
4,410.24 no
4,498.44 no
+2.0%
₹785
Anything above 8% is Contradicted. Cement does not evaporate — it walks out of the gate.