back to the stack
Unobservedscore 47.1 / 100 · updated 28 days ago

Tower A · Level 17

RCC frame — reported complete

Verdict override applied

Only 14% of claims on this floor carry evidence. Reported progress of 76% is unverified — this is not a low score, it is an absent one.

How this verdict was computed
BOQ quantity complete76×0.40
MB pages 180–219 · 5 items
Checklist pass rate0×0.20
no checklist filed
RA-bill certified0×0.20
nothing certified yet
NCR burden (inverted)85×0.10
0 NCRs on this floor
Schedule slip (inverted)82×0.10
programme baseline rev 4

Weighted score 47.1. Evidence coverage 14%. Two rules sit above this arithmetic: over 8% material variance or an open critical NCR forces Contradicted; under 30% evidence forces Unobserved regardless of how good the numbers look.

BOQ items on this floor
ItemPlannedMeasuredCertifiedVerdict
BOQ 4.2
RCC M25 in slabs, beams & landings incl. shuttering and finishing
80640Unobserved
BOQ 5.1
Brickwork 230mm thick in CM 1:6 with second class red bricks
78580Unobserved
BOQ 6.4
12mm cement plaster in CM 1:4 to internal walls
3002270Unobserved
BOQ 8.3
Vitrified tile flooring 600×600 laid on 20mm CM 1:4 bed
3012280Unobserved
BOQ 9.1
APP membrane waterproofing to toilets and terrace incl. screed
3312400Unobserved
Material reconciliation — theoretical vs actual
MaterialTheoreticalActualVarianceAt risk
OPC 53 cement
no issue slips filed
87.63 bag92.54 bag+5.6%₹2,008
TMT Fe550
no issue slips filed
3.16 T3.35 T+5.9%₹11,096
M-sand
no issue slips filed
24.84 T25.73 T+3.6%₹1,015
20mm aggregate
no issue slips filed
30.76 T31.9 T+3.7%₹1,117
Red brick
no issue slips filed
3,176.45 no3,322.57 no+4.6%₹1,300

Anything above 8% is Contradicted. Cement does not evaporate — it walks out of the gate.

Open non-conformances
No inspection on record

Zero NCRs here does not mean zero defects. Nobody has walked this floor with a checklist, so there is nothing to report either way. That is why this floor is grey.

Linked documents

One drawing and nothing else. No measurement book page, no goods receipt, no test certificate, no photograph. The site engineer reports 76% complete and there is no way to check.

Site photographs
No photographs captured on this floor in the last 30 days.