At Riskscore 76.3 / 100 · updated 3 days ago

Tower A · Level 6

Flooring & painting

How this verdict was computed
BOQ quantity complete73×0.40
MB pages 180–219 · 5 items
Checklist pass rate69×0.20
stage QA checklist register
RA-bill certified72×0.20
RA-06 certified abstract
NCR burden (inverted)96×0.10
4 NCRs on this floor
Schedule slip (inverted)93×0.10
programme baseline rev 4

Weighted score 76.3. Evidence coverage 83%. Two rules sit above this arithmetic: over 8% material variance or an open critical NCR forces Contradicted; under 30% evidence forces Unobserved regardless of how good the numbers look.

BOQ items on this floor
ItemPlannedMeasuredCertifiedVerdict
BOQ 4.2
RCC M25 in slabs, beams & landings incl. shuttering and finishing
725250Supported
BOQ 5.1
Brickwork 230mm thick in CM 1:6 with second class red bricks
685250Supported
BOQ 6.4
12mm cement plaster in CM 1:4 to internal walls
319223216Supported
BOQ 8.3
Vitrified tile flooring 600×600 laid on 20mm CM 1:4 bed
287206199Supported
BOQ 9.1
APP membrane waterproofing to toilets and terrace incl. screed
318239231Supported
Material reconciliation — theoretical vs actual
MaterialTheoreticalActualVarianceAt risk
OPC 53 cement
store issue register · 2 slips
94.33 bag98.2 bag+4.1%₹1,583
TMT Fe550
store issue register · 3 slips
2.88 T2.93 T+1.9%₹2,920
M-sand
store issue register · 11 slips
26.2 T26.88 T+2.6%₹775
20mm aggregate
store issue register · 11 slips
34.09 T35.28 T+3.5%₹1,166
Red brick
store issue register · 4 slips
3,150.09 no3,247.74 no+3.1%₹869

Anything above 8% is Contradicted. Cement does not evaporate — it walks out of the gate.

Open non-conformances
Linked documents
Site photographs
IMG-A-06-1
Slab soffit after de-shuttering, east bay
10 Aug 2026 · 09:12
12.9698°N 77.7500°E ±4m
IMG-A-06-2
Blockwork progress, units 03 & 04
11 Aug 2026 · 10:19
12.9698°N 77.7500°E ±5m
IMG-A-06-3
Reinforcement in place prior to pour, zone 2
12 Aug 2026 · 11:26
12.9698°N 77.7500°E ±6m