At Riskscore 69.6 / 100 · updated 3 days ago

Tower A · Level 8

Plaster & waterproofing

How this verdict was computed
BOQ quantity complete66×0.40
MB pages 180–219 · 5 items
Checklist pass rate68×0.20
stage QA checklist register
RA-bill certified62×0.20
RA-06 certified abstract
NCR burden (inverted)90×0.10
3 NCRs on this floor
Schedule slip (inverted)82×0.10
programme baseline rev 4

Weighted score 69.6. Evidence coverage 78%. Two rules sit above this arithmetic: over 8% material variance or an open critical NCR forces Contradicted; under 30% evidence forces Unobserved regardless of how good the numbers look.

BOQ items on this floor
ItemPlannedMeasuredCertifiedVerdict
BOQ 4.2
RCC M25 in slabs, beams & landings incl. shuttering and finishing
684541Supported
BOQ 5.1
Brickwork 230mm thick in CM 1:6 with second class red bricks
704642Supported
BOQ 6.4
12mm cement plaster in CM 1:4 to internal walls
301196180Supported
BOQ 8.3
Vitrified tile flooring 600×600 laid on 20mm CM 1:4 bed
289180166Supported
BOQ 9.1
APP membrane waterproofing to toilets and terrace incl. screed
278188173Supported
Material reconciliation — theoretical vs actual
MaterialTheoreticalActualVarianceAt risk
OPC 53 cement
store issue register · 2 slips
79.79 bag81.63 bag+2.3%₹753
TMT Fe550
store issue register · 9 slips
2.91 T2.96 T+1.8%₹2,920
M-sand
store issue register · 5 slips
25.3 T25.76 T+1.8%₹524
20mm aggregate
store issue register · 9 slips
27.06 T27.3 T+0.9%₹235
Red brick
store issue register · 11 slips
3,146.63 no3,184.39 no+1.2%₹336

Anything above 8% is Contradicted. Cement does not evaporate — it walks out of the gate.

Open non-conformances
Linked documents
Site photographs
IMG-A-08-1
Slab soffit after de-shuttering, east bay
10 Aug 2026 · 09:12
12.9698°N 77.7500°E ±4m
IMG-A-08-2
Blockwork progress, units 03 & 04
11 Aug 2026 · 10:19
12.9698°N 77.7500°E ±5m
IMG-A-08-3
Reinforcement in place prior to pour, zone 2
12 Aug 2026 · 11:26
12.9698°N 77.7500°E ±6m