Weighted score 94.4. Evidence coverage 97%. Two rules sit above this arithmetic: over 8% material variance or an open critical NCR forces Contradicted; under 30% evidence forces Unobserved regardless of how good the numbers look.
BOQ items on this floor
Item
Planned
Measured
Certified
Verdict
BOQ 4.2
RCC M25 in slabs, beams & landings incl. shuttering and finishing
80
76
68
Supported
BOQ 5.1
Brickwork 230mm thick in CM 1:6 with second class red bricks
65
67
60
Contradicted
BOQ 6.4
12mm cement plaster in CM 1:4 to internal walls
353
357
322
Supported
BOQ 8.3
Vitrified tile flooring 600×600 laid on 20mm CM 1:4 bed
282
264
238
Supported
BOQ 9.1
APP membrane waterproofing to toilets and terrace incl. screed
398
408
368
Contradicted
Material reconciliation — theoretical vs actual
Material
Theoretical
Actual
Variance
At risk
OPC 53 cement
store issue register · 11 slips
119.47 bag
119.71 bag
+0.2%
₹98
TMT Fe550
store issue register · 4 slips
4.18 T
4.16 T
-0.5%
—
M-sand
store issue register · 2 slips
37.13 T
37.06 T
-0.2%
—
20mm aggregate
store issue register · 2 slips
45.46 T
46.1 T
+1.4%
₹627
Red brick
store issue register · 10 slips
4,682.04 no
4,714.81 no
+0.7%
₹292
Anything above 8% is Contradicted. Cement does not evaporate — it walks out of the gate.