At Riskscore 59.3 / 100 · updated 3 days ago

Tower A · Level 11

Blockwork

How this verdict was computed
BOQ quantity complete55×0.40
MB pages 180–219 · 5 items
Checklist pass rate55×0.20
stage QA checklist register
RA-bill certified54×0.20
RA-06 certified abstract
NCR burden (inverted)80×0.10
4 NCRs on this floor
Schedule slip (inverted)75×0.10
programme baseline rev 4

Weighted score 59.3. Evidence coverage 69%. Two rules sit above this arithmetic: over 8% material variance or an open critical NCR forces Contradicted; under 30% evidence forces Unobserved regardless of how good the numbers look.

BOQ items on this floor
ItemPlannedMeasuredCertifiedVerdict
BOQ 4.2
RCC M25 in slabs, beams & landings incl. shuttering and finishing
623534Supported
BOQ 5.1
Brickwork 230mm thick in CM 1:6 with second class red bricks
724139Supported
BOQ 6.4
12mm cement plaster in CM 1:4 to internal walls
353200192Supported
BOQ 8.3
Vitrified tile flooring 600×600 laid on 20mm CM 1:4 bed
293161155Supported
BOQ 9.1
APP membrane waterproofing to toilets and terrace incl. screed
296157151Supported
Material reconciliation — theoretical vs actual
MaterialTheoreticalActualVarianceAt risk
OPC 53 cement
store issue register · 9 slips
70.46 bag72.86 bag+3.4%₹982
TMT Fe550
store issue register · 7 slips
2.41 T2.49 T+3.4%₹4,672
M-sand
store issue register · 5 slips
18.41 T18.96 T+3.0%₹627
20mm aggregate
store issue register · 5 slips
23.58 T24.19 T+2.6%₹598
Red brick
store issue register · 8 slips
2,515.88 no2,563.68 no+1.9%₹425

Anything above 8% is Contradicted. Cement does not evaporate — it walks out of the gate.

Open non-conformances
Linked documents
Site photographs
IMG-A-11-1
Slab soffit after de-shuttering, east bay
10 Aug 2026 · 09:12
12.9698°N 77.7500°E ±4m
IMG-A-11-2
Blockwork progress, units 03 & 04
11 Aug 2026 · 10:19
12.9698°N 77.7500°E ±5m
IMG-A-11-3
Reinforcement in place prior to pour, zone 2
12 Aug 2026 · 11:26
12.9698°N 77.7500°E ±6m