back to the stack
At Riskscore 55.0 / 100 · updated 3 days ago

Tower A · Level 13

RCC frame

How this verdict was computed
BOQ quantity complete48×0.40
MB pages 180–219 · 5 items
Checklist pass rate43×0.20
stage QA checklist register
RA-bill certified45×0.20
RA-06 certified abstract
NCR burden (inverted)98×0.10
4 NCRs on this floor
Schedule slip (inverted)84×0.10
programme baseline rev 4

Weighted score 55.0. Evidence coverage 53%. Two rules sit above this arithmetic: over 8% material variance or an open critical NCR forces Contradicted; under 30% evidence forces Unobserved regardless of how good the numbers look.

BOQ items on this floor
ItemPlannedMeasuredCertifiedVerdict
BOQ 4.2
RCC M25 in slabs, beams & landings incl. shuttering and finishing
582927Supported
BOQ 5.1
Brickwork 230mm thick in CM 1:6 with second class red bricks
743431Supported
BOQ 6.4
12mm cement plaster in CM 1:4 to internal walls
335170156Supported
BOQ 8.3
Vitrified tile flooring 600×600 laid on 20mm CM 1:4 bed
296136125Supported
BOQ 9.1
APP membrane waterproofing to toilets and terrace incl. screed
256118108Supported
Material reconciliation — theoretical vs actual
MaterialTheoreticalActualVarianceAt risk
OPC 53 cement
store issue register · 10 slips
54.48 bag55.41 bag+1.7%₹380
TMT Fe550
store issue register · 4 slips
1.95 T1.99 T+2.3%₹2,336
M-sand
store issue register · 8 slips
16.29 T16.44 T+0.9%₹171
20mm aggregate
store issue register · 6 slips
22.38 T22.89 T+2.3%₹500
Red brick
store issue register · 3 slips
2,245.43 no2,265.64 no+0.9%₹180

Anything above 8% is Contradicted. Cement does not evaporate — it walks out of the gate.

Open non-conformances
Linked documents
Site photographs
IMG-A-13-1
Slab soffit after de-shuttering, east bay
10 Aug 2026 · 09:12
12.9698°N 77.7500°E ±4m
IMG-A-13-2
Blockwork progress, units 03 & 04
11 Aug 2026 · 10:19
12.9698°N 77.7500°E ±5m
IMG-A-13-3
Reinforcement in place prior to pour, zone 2
12 Aug 2026 · 11:26
12.9698°N 77.7500°E ±6m