Weighted score 87.5. Evidence coverage 96%. Two rules sit above this arithmetic: over 8% material variance or an open critical NCR forces Contradicted; under 30% evidence forces Unobserved regardless of how good the numbers look.
BOQ items on this floor
Item
Planned
Measured
Certified
Verdict
BOQ 4.2
RCC M25 in slabs, beams & landings incl. shuttering and finishing
55
50
48
Supported
BOQ 5.1
Brickwork 230mm thick in CM 1:6 with second class red bricks
64
57
55
Supported
BOQ 6.4
12mm cement plaster in CM 1:4 to internal walls
380
339
324
Supported
BOQ 8.3
Vitrified tile flooring 600×600 laid on 20mm CM 1:4 bed
307
268
257
Supported
BOQ 9.1
APP membrane waterproofing to toilets and terrace incl. screed
325
289
277
Supported
Material reconciliation — theoretical vs actual
Material
Theoretical
Actual
Variance
At risk
OPC 53 cement
store issue register · 4 slips
103.79 bag
106.07 bag
+2.2%
₹933
TMT Fe550
store issue register · 9 slips
3.47 T
3.46 T
-0.2%
—
M-sand
store issue register · 9 slips
31.42 T
32.02 T
+1.9%
₹684
20mm aggregate
store issue register · 9 slips
36.7 T
37.07 T
+1.0%
₹363
Red brick
store issue register · 9 slips
4,201.03 no
4,301.85 no
+2.4%
₹897
Anything above 8% is Contradicted. Cement does not evaporate — it walks out of the gate.