At Riskscore 70.8 / 100 · updated 2 days ago

Tower B · Level 6

Blockwork & plaster

How this verdict was computed
BOQ quantity complete68×0.40
MB pages 180–219 · 5 items
Checklist pass rate66×0.20
stage QA checklist register
RA-bill certified64×0.20
RA-06 certified abstract
NCR burden (inverted)90×0.10
3 NCRs on this floor
Schedule slip (inverted)86×0.10
programme baseline rev 4

Weighted score 70.8. Evidence coverage 81%. Two rules sit above this arithmetic: over 8% material variance or an open critical NCR forces Contradicted; under 30% evidence forces Unobserved regardless of how good the numbers look.

BOQ items on this floor
ItemPlannedMeasuredCertifiedVerdict
BOQ 4.2
RCC M25 in slabs, beams & landings incl. shuttering and finishing
805248Supported
BOQ 5.1
Brickwork 230mm thick in CM 1:6 with second class red bricks
664340Supported
BOQ 6.4
12mm cement plaster in CM 1:4 to internal walls
277181167Supported
BOQ 8.3
Vitrified tile flooring 600×600 laid on 20mm CM 1:4 bed
311201185Supported
BOQ 9.1
APP membrane waterproofing to toilets and terrace incl. screed
343226208Supported
Material reconciliation — theoretical vs actual
MaterialTheoreticalActualVarianceAt risk
OPC 53 cement
store issue register · 9 slips
76.06 bag78.57 bag+3.3%₹1,027
TMT Fe550
store issue register · 3 slips
2.59 T2.66 T+2.7%₹4,088
M-sand
store issue register · 4 slips
26.83 T27.58 T+2.8%₹855
20mm aggregate
store issue register · 10 slips
31.79 T32.46 T+2.1%₹657
Red brick
store issue register · 9 slips
3,333.19 no3,413.19 no+2.4%₹712

Anything above 8% is Contradicted. Cement does not evaporate — it walks out of the gate.

Open non-conformances
Linked documents
Site photographs
IMG-B-06-1
Slab soffit after de-shuttering, east bay
10 Aug 2026 · 09:12
12.9698°N 77.7500°E ±4m
IMG-B-06-2
Blockwork progress, units 03 & 04
11 Aug 2026 · 10:19
12.9698°N 77.7500°E ±5m
IMG-B-06-3
Reinforcement in place prior to pour, zone 2
12 Aug 2026 · 11:26
12.9698°N 77.7500°E ±6m