At Riskscore 67.1 / 100 · updated 2 days ago

Tower B · Level 7

Blockwork & plaster

How this verdict was computed
BOQ quantity complete62×0.40
MB pages 180–219 · 5 items
Checklist pass rate63×0.20
stage QA checklist register
RA-bill certified60×0.20
RA-06 certified abstract
NCR burden (inverted)87×0.10
0 NCRs on this floor
Schedule slip (inverted)90×0.10
programme baseline rev 4

Weighted score 67.1. Evidence coverage 75%. Two rules sit above this arithmetic: over 8% material variance or an open critical NCR forces Contradicted; under 30% evidence forces Unobserved regardless of how good the numbers look.

BOQ items on this floor
ItemPlannedMeasuredCertifiedVerdict
BOQ 4.2
RCC M25 in slabs, beams & landings incl. shuttering and finishing
784644Supported
BOQ 5.1
Brickwork 230mm thick in CM 1:6 with second class red bricks
674341Supported
BOQ 6.4
12mm cement plaster in CM 1:4 to internal walls
345209198Supported
BOQ 8.3
Vitrified tile flooring 600×600 laid on 20mm CM 1:4 bed
312203193Supported
BOQ 9.1
APP membrane waterproofing to toilets and terrace incl. screed
400255242Supported
Material reconciliation — theoretical vs actual
MaterialTheoreticalActualVarianceAt risk
OPC 53 cement
store issue register · 5 slips
71.19 bag75.53 bag+6.1%₹1,775
TMT Fe550
store issue register · 6 slips
2.54 T2.58 T+1.6%₹2,336
M-sand
store issue register · 6 slips
22 T22.77 T+3.5%₹878
20mm aggregate
store issue register · 5 slips
26.13 T27.41 T+4.9%₹1,254
Red brick
store issue register · 5 slips
2,714.51 no2,825.8 no+4.1%₹990

Anything above 8% is Contradicted. Cement does not evaporate — it walks out of the gate.

Open non-conformances
No inspection on record

Zero NCRs here does not mean zero defects. Nobody has walked this floor with a checklist, so there is nothing to report either way. That is why this floor is grey.

Linked documents
Site photographs
IMG-B-07-1
Slab soffit after de-shuttering, east bay
10 Aug 2026 · 09:12
12.9698°N 77.7500°E ±4m
IMG-B-07-2
Blockwork progress, units 03 & 04
11 Aug 2026 · 10:19
12.9698°N 77.7500°E ±5m
IMG-B-07-3
Reinforcement in place prior to pour, zone 2
12 Aug 2026 · 11:26
12.9698°N 77.7500°E ±6m
IMG-B-07-4
Toilet waterproofing ponding test in progress
13 Aug 2026 · 12:33
12.9698°N 77.7500°E ±7m