back to the stack
At Riskscore 39.3 / 100 · updated 2 days ago

Tower B · Level 10

Slab shuttering

How this verdict was computed
BOQ quantity complete30×0.40
MB pages 180–219 · 5 items
Checklist pass rate29×0.20
stage QA checklist register
RA-bill certified28×0.20
RA-06 certified abstract
NCR burden (inverted)77×0.10
1 NCRs on this floor
Schedule slip (inverted)82×0.10
programme baseline rev 4

Weighted score 39.3. Evidence coverage 33%. Two rules sit above this arithmetic: over 8% material variance or an open critical NCR forces Contradicted; under 30% evidence forces Unobserved regardless of how good the numbers look.

BOQ items on this floor
ItemPlannedMeasuredCertifiedVerdict
BOQ 4.2
RCC M25 in slabs, beams & landings incl. shuttering and finishing
722119Supported
BOQ 5.1
Brickwork 230mm thick in CM 1:6 with second class red bricks
702018Supported
BOQ 6.4
12mm cement plaster in CM 1:4 to internal walls
397121111Supported
BOQ 8.3
Vitrified tile flooring 600×600 laid on 20mm CM 1:4 bed
3169486Supported
BOQ 9.1
APP membrane waterproofing to toilets and terrace incl. screed
2637670Supported
Material reconciliation — theoretical vs actual
MaterialTheoreticalActualVarianceAt risk
OPC 53 cement
store issue register · 11 slips
38.79 bag38.71 bag-0.2%
TMT Fe550
store issue register · 8 slips
1.32 T1.32 T-0.3%
M-sand
store issue register · 4 slips
11.83 T11.84 T+0.1%₹11
20mm aggregate
store issue register · 6 slips
12.23 T12.1 T-1.1%
Red brick
store issue register · 10 slips
1,266.06 no1,255.93 no-0.8%

Anything above 8% is Contradicted. Cement does not evaporate — it walks out of the gate.

Open non-conformances
Linked documents
Site photographs
IMG-B-10-1
Slab soffit after de-shuttering, east bay
10 Aug 2026 · 09:12
12.9698°N 77.7500°E ±4m
IMG-B-10-2
Blockwork progress, units 03 & 04
11 Aug 2026 · 10:19
12.9698°N 77.7500°E ±5m
IMG-B-10-3
Reinforcement in place prior to pour, zone 2
12 Aug 2026 · 11:26
12.9698°N 77.7500°E ±6m